The Ghana Grid Company Limited (GRIDCo) has completed repairs to the damaged 330kV Aboadze–Anwomaso transmission line, restoring electricity transmission after an outage disrupted power supply to parts of the Western and Ashanti regions.
The transmission line was damaged on Wednesday, November 25, 2026, after a tree reportedly fell onto the power infrastructure during illegal chainsaw operations, affecting electricity distribution in the two regions.
In a statement issued on Thursday, November 26, GRIDCo confirmed that repair works had been completed at approximately 12:07 p.m., enabling the transmission line to resume full operations.
The company said the restoration followed repair efforts to address the damage and restore normal electricity transmission along the affected route.
GRIDCo urged members of the public to refrain from illegal chainsaw activities and other operations near high-voltage transmission lines and related facilities to prevent similar incidents.
The company further appealed for public cooperation in protecting critical electricity infrastructure, warning that activities around transmission corridors could disrupt power supply.
GRIDCo also expressed appreciation to electricity consumers affected by the disruption for their patience, cooperation and understanding while repair works were underway.
The restoration brings relief to affected consumers in the Western and Ashanti regions following the disruption caused by the damaged transmission line.